Construction loan calculator
A construction facility is drawn down as the build progresses, so interest accrues on the average balance rather than the commitment. This calculator sizes the interest reserve, the equity gap and the loan-to-cost ratio that lenders underwrite to.
| Item | Amount |
|---|---|
| Total development cost | $10,000,000 |
| Loan commitment | $8,000,000 |
| Equity required | $2,000,000 |
| Interest reserve | $320,000 |
| Total debt | $8,320,000 |
| Interest as % of loan | 4.0% |
Interest is capitalised into the facility, which is standard for construction lending.
loan × rate × months/12 × average draw · 50% average draw is the usual planning assumption.
loan / total cost · Typically capped at 65–80%.
capitalised into the facility · Paid from the loan, not by the borrower upfront.
A clear path from inputs to results.
A construction facility is drawn down as the build progresses, so interest accrues on the average balance rather than the commitment. This calculator sizes the interest reserve, the equity gap and the loan-to-cost ratio that lenders underwrite to.
How to use
- Enter the total development cost.
- Set the loan commitment.
- Enter the rate and the build period.
- Read the interest reserve, LTC and equity requirement.
The formula
Reference: Interest capitalised on the average outstanding balance, the standard construction draw convention (Broverman, Mathematics of Investment and Credit).
Worked example
$10M cost, $8M loan, 8%, 12 months
- Total cost $10,000,000.
- Loan $8,000,000.
- Rate 8%.
- Build period 12 months.
- 1
Average draw 50%, so average balance $4,000,000.
- 2
Interest: 8,000,000 × 0.08 × 1 × 0.5 = $320,000.
- 3
Total repayment: $8,320,000.
- 4
Loan-to-cost: 80%.
- 5
Equity required: $2,000,000, plus the interest if it is not capitalised.
Interest reserve $320,000 · LTC 80% · equity $2M.
Interpreting the result
The interest reserve is the line item sponsors underestimate. A twelve-month build at 8% costs 4% of the loan; a delayed build costs proportionally more, and the reserve is usually the first thing to run dry.
Assumptions & limitations
- Interest capitalised into the facility.
- Average draw of 50% over the build.
- No fees, carry or extension costs.
- Single draw curve; real projects draw against completed work.
Frequently asked questions
Why 50% average draw?
Draws typically follow an S-curve, so the average outstanding balance is around half the commitment.
What if the build runs late?
Interest accrues for longer; the calculator lets you extend the build period to see the cost.
Is LTC the same as LTV?
No. LTC is against cost during construction; LTV is against value after completion.
Methodology last reviewed 2026-10-21. Results are informational and not financial or engineering advice — see our disclaimer.